ICON Engineering was engaged to install the Buffalo Field wellhead
platform in 30m of water in the Timor Sea north of Darwin Australia.
ICON assisted with the preparation of the installation
contracts for the FPSO and infield pipelines and interfaced directly
with BHPP's drilling department on issues relating to the use of the
jackup rig Ron Tappmeyer for the installation work.
| |
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|

ICON Engineering was engaged by Talisman Malaysia to undertake
the installation engineering for the MOAB structure at the Bunga Raya
field. ICON Engineering developed the installation procedures including
detailed stability analysis for the tow and sinking of the substructure.
ICON Engineering performed geotechnical installation analysis, selected
the suction pumps for installation of the suction piles and designed
the ballasting umbilical system.
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|

ICON Engineering was commissioned by Shell to provide assistance
with the installation of the Skiff platform in the Southern North Sea.
The platform was installed by a jackup drilling rig. This was the first
platform to be installed by this means in the UK sector of the North
Sea. The installed cost was a fraction of that required using conventional methods
The project won the British Government Construction Industry Civil Engineering
Award for 2000 in recognition of the novel design and installation method
which challenged traditional practices.
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|

ICON Engineering was commissioned to install the 220 tonne topsides
using the Jackup Rig "Trident 17" operated by Sedco Forex and
to coordinate the interfaces between the Jackup operator, IPC drilling
department, IPC Project Group and topsides fabricator and FPSO/flowline
installation contractor. The complete
topsides installation was carried out in a single day.
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|

ICON founders, Garrick Aberle and David Field were respectively the
Project Manager and Designer / Senior Installation Engineer for this
project. The development consists of 4 monopod platforms, two subsea
pipelines and shore based oil separation nad gas sales conditioning
facilities.
The 26 km long, 3 phase, 26” diameter production line and 36 km
long, 6” gas export line were constructed using the beach pulled
/ bottom tow method. At the time, this was one of the longest pipelines
in the world constructed in this manner.

| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|